Wednesday, February 26, 2014

Makin' Ice and The Last New Walls Go Up!

We have flooded twice and started to make ice! Yes, after the ice plant was turned on for a few days and the sand reached a cool enough temperature, it's finally time to make the layers of ice!


The last new walls are being finished in the Equipment Room cutting around a lot of pipes in the ceiling. 


We are so tired of cutting around pipes...Hang in there! Last one. :)


The ADA concrete ramps are poured, the ADA bathrooms are coming along (no picture for obvious reasons...who really wants to see toilets ripped out?), ADA water fountain installed.


And the back of the ice wall gets it's vapor barrier and the last round of firewall drywall (jib board).

Time to call it another night to be awake for work tomorrow! Every day we make visual progress closer to opening!

2 comments:

  1. I am sooooo impressed by how much of the work is being done by club members!

    ReplyDelete
  2. I just drove by your building yesterday (I work 1 block away) and was gobsmacked that there was curling in Tempe. My lover and I have been watching all the recorded Olympic curling events (only about half done) this year and talking about how it would be fun to try to play.

    ReplyDelete